Notice of utility diversion works near Tolldish Lane, Great Haywood

Work item: HS2-MW-UT-Ph1-Ar-No-N2-UT-11-31/01/2023

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
A51, Tolldish Lane
Worksite Name
A51, Tolldish Lane
Contractor
Cadent Gas
Type of works
Gas pipeline diversion
Estimated Start Date
20/02/2023
Estimated End Date
31/10/2023

What we are doing

Cadent will be using the existing HS2 works compound and site access off Tolldish lane to carry out the diversion. Cadent will be starting preparation activities on land off Tolldish Lane in late February 2023.

This will involve securing the working area with fencing and carrying out the removal of some vegetation and trees. Cadent will carry out appropriate ecological surveys before any vegetation clearance with an ecologist present throughout the activity to ensure there is no disruption to birds and local wildlife.

Cadent will then begin work to move the pipeline in March 2023.

The work will involve:

  • Digging a trench for the new pipeline off Common Lane
  • Welding the pipe together then installing it in the trench
  • Connecting and testing the new pipe

Vehicles will be accessing our working area from Tolldish Lane, via the A51.  Signage will be installed on the roadside at the site entrance, to ensure safe access and exit for vehicles.