Notice of utility diversions on A452 Chester Road

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-43-05/11/2023

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
A452
Worksite Name
A452 Chester Road
Contractor
BBV JV
Type of works
Lane closure, Utility works / surveys
Estimated Start Date
30/10/2023
Estimated End Date
22/12/2023

What we are doing

Owing to unforeseen challenges, our A452 Chester Road phased lane closures will need to be extended from 30 October 2023 to 3 November 2023.

To minimise our impact on the road network, we have been carrying out our utility diversion in phases. Once we have completed the works on A452 Chester Road, we will commence work on Cadbury Drive.

Two way temporary traffic lights will be used during this period on Tameside Drive. We now expect the utility diversions to be completed and the traffic management on Tameside Drive and Cadbury Drive to be removed on 22 December 2023.

Access for residents and businesses will be maintained at all times.