Notice of utility diversions on Tameside Drive
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-UT-42-04/11/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Bromford
- Contractor
- BBV JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 27/04/2023
- Estimated End Date
- 25/05/2023
What we are doing
In order to construct the railway we need to carry out a programme of utility diversions. Initially, these will take place on Tameside Drive from Thursday 27 April for approximately 4 weeks. Following this, there will be utility diversions on the A452 Chester Road, however, we will notify you of these works nearer the time.
To carry out the utility diversions safely, we need to manage traffic and pedestrians in the area. We’ll carry out the utility diversions in phases, rather than all at once, to keep disruption to a minimum.
Tameside Drive: Phase 1
During this phase of work, there will be temporary traffic signals in place and operatives on site throughout to ensure safe access is maintained at all times (please see the map on page 2 for the location of the works).
These works will take place between the hours of 8am and 6pm from Monday to Saturday.
Tameside Drive: Phase 2
During this phase of work, there will be temporary traffic signals in place and operatives on site throughout to ensure safe access is maintained at all times (please see the map on page 2 for the location of the works).
These works will take place between the hours of 8pm and 6am from Monday to Friday.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]