Skip to main page content
View route map

Notice of utility surveys at Hanger Lane roundabout

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-08/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Ealing
Worksite Name
Westgate
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
26/09/2022
Estimated End Date
28/10/2022

What we are doing

Works planned on Hanger Lane Roundabout

Between 26 September to 28 October 2022, we will be carrying out a series of overnight ground investigations on the Hanger Lane Roundabout. The ground investigations will take place between 10pm to 6am Monday to Saturday.

The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road and footpath. The investigations will help us to understand and aid the design of the new railway and the best ways to protect or divert any utilities during construction.

We will be working as efficiently as possible whilst keeping our work areas safe and tidy.

How this might affect you

To ensure the safety of the public and our staff, temporary changes will be in place on the Hanger Lane Roundabout.

We will have bus lane and lane closures in place overnight. The  footpath closures will be in place overnight and during the day, pedestrians will be able to use the subway during these works. You can view the different traffic management phases on the following pages.

Your utility services will not be affected during these works.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]