Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-3-7/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Canterbury Road
- Worksite Name
- Canterbury Works
- Contractor
- SCS JV
- Type of works
- Survey
- Estimated Start Date
- 25/07/2022
- Estimated End Date
- 28/07/2022
What we are doing
Drainage surveys within Carlton House green spaces
On 25 July 2022 between the hours of 8am to 6pm, we will be carrying out a series of drainage surveys within the green spaces on the Carlton House estate on Canterbury Terrace.
These surveys will help us understand the condition of the drainage system in the area and how to best protect them during the construction of the railway. We will investigate the condition of the sewer system using a camera. We may also need to flush the drainage within the sewer system using a high-pressure water jet if any blockages are found. You may notice additional noise should we need to carry out this activity.
Your utility services will not be affected during the surveys.
What to expect
In order to carry out these works safely, we will set up a small safety zone around our working area. We will need to temporarily suspend some parking bays on Canterbury Terrace to park the water tanker in various locations as we move up the road. The works will not affect pedestrian and vehicle access. Signage will be in place to advise motorists and pedestrians of our work. A map showing the location of these works can be viewed on page 2.
Overnight drainage surveys planned on Canterbury Road
From 25 to 29 July 2022 between 8pm and 6am, we will be carrying out overnight surveys on Canterbury Road on the junction with Chichester Road as shown on the map below.
The surveys will help us to understand the condition of the drainage system in the area and how best to protect them during the construction of the railway. We will investigate the manhole using a 3D camera scanner to capture internal dimensions and the condition of the sewer system. Once completed, we will replace the manhole cover.
We will have a temporary lane closure and traffic lights in place on Canterbury Road on the junction with Chichester Road.
Speak to our local engagement team
Your local engagement team are happy to speak with you in person or virtually about any questions or concerns you have about our works in your local area.
We hold virtual drop-ins on the third Wednesday of each month. Our next virtual drop in is on Wednesday 20 July 2022– you can register to attend at www.hs2.org.uk/events/
Please contact the HS2 Helpdesk If you are not able to attend the virtual drop-in and would like to speak with us at another time.
We are also planning on holding face-to-face drop-ins from summer 2022 and will let the community know when the details are confirmed.