Notice of utility surveys in your local area
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-1-22/06/22
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Canterbury Road
- Worksite Name
- Canterbury Works
- Contractor
- SCS JV
- Type of works
- Ground investigations
- Estimated Start Date
- 11/07/2022
- Estimated End Date
- 29/07/2022
What we are doing
Works planned on Greville Road and Kilburn High Road
From 11 to 29 July 2022, we will be carrying out a series of ground investigations at the junction of Greville Road and Kilburn High Road. The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road. The investigations will help us to understand and aid the design of the new railway and the best ways to protect or divert any utilities during construction. Your utility services will not be affected during these works.
The ground investigations will take place between 8am to 6pm Monday to Friday and 8am to 1pm Saturdays, if required. We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.
How this might affect you
To ensure the safety of the public and our staff, temporary changes will be in place at the junction of Greville Road and Kilburn High Road (shown on the following page).
A lane closure with two-way traffic lights will be in place on Kilburn High Road with a full road closure on the junction of Greville Road with Kilburn High Road . A clearly singed diversion route for vehicles and pedestrians will be in place.
Map showing the temporary changes on Greville Road and Kilburn High Road
To help us maintain traffic flow on the road network, we have agreed the following diversion route:
Vehicles travelling west on Greville Road will be diverted northwest onto Kilburn Priory, east along
Belsize Road and then south on Kilburn High Road. Vehicles travelling north on Kilburn High Road will be diverted west along Belsize Road and then south on Kilburn Priory.
Access to businesses and homes will be available at all times.