Notice of Utility Surveys in your local area

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-1-05/01/23

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden
Worksite Name
Adelaide Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
23/01/2023
Estimated End Date
04/02/2023

What we are doing

Ground investigations in your area
From 23 January to 4 February 2023 (Phase 1), and 6 February to 24 February 2023 (Phase 2) we will be carrying out a series of ground investigations on Finchley Road, College Crescent, and Avenue Road.

The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road. The investigations will help us to understand and aid the design of the new railway and the best ways to protect or divert any utilities during construction. Your utility services will not be affected during these works.

The ground investigations will take place between 8am to 6pm Monday to Friday and 8am to 1pm Saturdays, if required. We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.

How will this affect you
To ensure the safety of the public and our staff, temporary changes will be in place on Finchley Road and surrounding roads (shown on the following page). The temporary changes will occur in two phases;

Phase 1: Lane closures on Finchley Road and Harben Parade, and partial road closures on College Crescent and Avenue Road. Bus stop and parking suspensions will be in place on Finchley Road, Harben Parade and College Crescent.

Phase 2: Lane closures on Finchley Road, Avenue Road, and College Crescent alongside partial road closures on Finchley Road. Parking and loading bay suspensions will be in place on Finchley Road.

Clearly signed diversion routes for vehicles and pedestrians will be in place.

Download information relating to these works

Find out more about