Notice of utility surveys on Greenford Road and Lyon Way

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-5-19/05/2021

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Greenford
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
19/05/2021
Estimated End Date
26/05/2021

What we are doing

Surveys planned between 19 and 26 May

From 19 to 26 May 2021, we will be carrying out drainage surveys on Greenford Road, Rockware Avenue and Lyon Way. The surveys are planned to take place during the day from 8am to 6pm. We will use a camera to investigate the condition of the drainage system and may need to flush the drains using a high-pressure water jet.

How might this affect you

Between 19 and 21 May, temporary lane closures will be in place during the day on Greenford Road and near the junctions of Uneeda Drive and Bennetts Avenue. Parking bay suspensions will be in place on Greenford Road.

On 24 May, temporary lane closures will be in place on the junction of Greenford Road and Rockware Avenue.

On 25 and 26 May, temporary lane closures will be in place on Lyon Way

The maps on the following pages show the location of these temporary changes during each phase of the works.

Your utility services will not be affected during the surveys and you will still be able to travel through this area. The dates and locations for the surveys could change and we may need to carry out further surveys in your area. To sign up for updates, please visit www.hs2inkilburn-northolt.co.uk.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]