Notice of Utility Works at Bockendon Grange, Kenilworth

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-UT-8-15/06/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Kenilworth
Contractor
Western Power Distribution
Type of works
Cable works
Estimated Start Date
04/07/2022
Estimated End Date
19/09/2022

What we are doing

What are we doing?

Western Power Distribution (WPD) will be diverting their existing overhead line (OHL), to underground line, this is to avoid the HS2 route.

This work will involve completing a Horizontal Directional Drill (HDD) under the Kenilworth Greenway and future HS2 track. Some underground cable works and the removal of redundant OHL will also be completed.

How will this impact you?

The works will commence on the 4 July 2022 and will last for 10 weeks. This will include weekend working on 16 and 17 July, 30 and 31 July and 13 and 14 August.

There will be minimal impact on the surrounding area. The work requires plant and equipment to be on site and will be carried out in fields away from residents and the highway.

Core working hours will be between 8am and 6pm. WPD may be on site up to one hour before and one hour after to set up and secure the site