Notice of Utility Works at Duddeston Mill Road, Birmingham
Work item: HS2-EW-OTH-Ph1-Bir-Cur-St-N4-UT-8-22/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Saltley
- Contractor
- WPD
- Type of works
- Utility works / surveys
- Estimated Start Date
- 17/05/2021
- Estimated End Date
- 04/06/2021
What we are doing
Western Power Distribution (WPD) will be undertaking trial holes on Duddeston Mill Road at the entrance to Network Rail Saltley Depot. This work includes the excavation of material in a segregated works area and reinstatement. All works will be segregated from vehicle or pedestrian access and sign posted. Any changes to footpaths or vehicle routes will be signposted at location in line with agreed traffic management requirements. Once completed all locations will be put back as new. No outages will take place during the works.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]