Notice of Utility Works – Gilson area
Work item: HS2-MW-UT-Ph1-Ar-No-N1-OTH-30-09/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Gilson
- Contractor
- Severn Trent Water
- Type of works
- Utility works / surveys
- Estimated Start Date
- 03/10/2022
- Estimated End Date
- 16/12/2022
What we are doing
This work is subject to receiving consent for 24 hour operation.
Severn Trent has been asked to carry out a diversion of a strategic sewer that is currently located in the way of the HS2 railway line.
The sewer diversion will start in the fields just to the south of Coleshill Manor, then head north-east crossing under the M42 motorway, and then head north along the eastern side of Gilson, ending just to the north of the village.
Due to the make-up of the soil in this area, part of the tunnelling works requires 24 hour working. We will be working in this area between Monday 3 October until Friday 16 December 2022. The plan overleaf shows where this 24-hour work will be carried out.
Severn Trent has a responsibility for delivering water and sewerage services to homes and businesses across the region and to ensure the impact of any work is kept to a minimum.
The work will generate a small amount of noise and dust, but we will do our best to keep this to an absolute minimum.
There will be no impact on your water or sewerage services.