Work item: HS2-MW-LM-Ph1-Bir-Cur-St-N4-UT-37-08/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Birmingham
- Worksite Name
- Curzon Station
- Contractor
- LM JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 15/11/2021
- Estimated End Date
- 17/12/2021
What we are doing
We’ll be carrying out utility works on Masshouse Lane and Albert Street Over the coming months, we’ll continue to work on roads in central Birmingham and carry out a programme of utility diversions as we prepare for the construction of HS2’s Curzon Street Station and the railway.
From Monday 15 November for approximately 4 weeks, subject to weather, site and other conditions. Our working hours will be between 8am and 6pm. We may be on site up to an hour before or after our working hours.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]