- Project Phase
- Phase 1
- Region
- Camden
- Location
- Euston Street, North Gower Street, Starcross Street
- Worksite Name
- Euston Station
- Contractor
- Mace Dragados JV
- Type of works
- Gas Main Works, Utility Works
- Estimated Start Date
- 07/04/2025
- Estimated End Date
- 23/12/2025
What we are doing
Euston utility works
As part of our essential programme of works, we are continuing with utility works in the local area starting in April 2025 and continuing into the winter 2025. Please read the rest of this notice to find out more about works taking place on Euston Street, Starcross Street, and South Cobourg Street.
Starcross Street UKPN Works
A new UKPN power station is being installed at the Maria Fidelis Old School site. To facilitate this, we will be extending our hoarding on Starcross Street, which will require the temporary suspension of two car park spaces. These works will commence on Monday, 7 April 2025, and will last for ten weeks.
Please find the link below for more information.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]