Notice of Utility Works off Coleshill Road, Water Orton June-November 2021

Work item: HS2-EW-UT-Ph1-Ar-No-N2-UT-22-21/05/2021

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Water Orton
Contractor
WPD
Estimated Start Date
14/06/2021
Estimated End Date
30/11/2021

What we are doing

In order to construct the proposed embankments associated with the main HS2 tracks at Coleshill Road, Western Power Distribution (WPD) will need to divert an existing high voltage cable circuit from Lea Marston to Kitts Green.

The works will begin 14 June 2021 and are expected to last until November 2021 and the works will consist of excavation and installation of high voltage cables.