Notice of Utility Works off Coleshill Road, Water Orton June-November 2021
Work item: HS2-EW-UT-Ph1-Ar-No-N2-UT-22-21/05/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Water Orton
- Contractor
- WPD
- Estimated Start Date
- 14/06/2021
- Estimated End Date
- 30/11/2021
What we are doing
In order to construct the proposed embankments associated with the main HS2 tracks at Coleshill Road, Western Power Distribution (WPD) will need to divert an existing high voltage cable circuit from Lea Marston to Kitts Green.
The works will begin 14 June 2021 and are expected to last until November 2021 and the works will consist of excavation and installation of high voltage cables.