Notice of utility works on Park Royal Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-OTH-1-14/06/2023

Work Item Summary

Project Phase
Phase 1
Location
Park Royal
Worksite Name
Park Royal Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
23/06/2023
Estimated End Date
07/08/2023

What we are doing

From 23 June to 7 August 2023, we will be carrying out over pumping works on the main sewer pipe on Park Royal Road.

Over pumping is needed when an existing sewer or storm water network needs upgrading but cannot be turned off.

To ensure the safety of our operatives and the public, we will have various phases of traffic management in place on Park Royal Road which is outlined below:

  • From 6pm on 23 June to 6am on 25 June 2023, we will have a temporary road closure in place between the entrance to Lower Park Business Estate and Gorst Road.
  • From 6am on 25 June to 6pm on 4 August, we will have a temporary footpath closure on Park Royal Road. Two-way traffic will still be able to move through the area during this time. Pedestrian crossings will be available at both end of the traffic management.
  • From 6pm on 4 August to 6am on 7 August 2023, we will have a temporary road closure in place between the entrance to Lower Park Business Estate and Gorst Road.