View route map
Notice of utility works on Victoria Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-11/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Victoria Road
- Worksite Name
- Victoria Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 18/08/2023
- Estimated End Date
- 20/08/2023
What we are doing
From 11 to 13 August 2023 we will be carrying out works to protect the utility services below Victoria Road and the surrounding areas ahead of future tunnelling works.
The works will take place between 8am to 6pm Monday to Friday and 8am to 1pm Saturdays, if required.
Your utility services will not be affected during these works.