Notice of Utility Works on Victoria Road, North Acton

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-28/11/2023

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Victoria Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
08/01/2024
Estimated End Date
05/06/2024

What we are doing

Between 8 January 2024 and 5 June 2024, we will be carrying out utility works to install a new cable diversion under Victoria Road. The planned works will include excavation and resurfacing of the road, and cabling works to create the diversion. These works will be carried out in phases.

Working Hours

Due to anticipated network requirements, our working hours will be as follows:

  • From 8 January to 26 March 2024, 8am to 6pm, Monday to Friday and 8am to 1pm on weekends, and
  • From 27 March to 5 June 2024, 8am to 10pm, Monday to Friday and 8am to 6pm on weekends.