View route map
Notice of Utility Works on Victoria Road, North Acton
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-28/11/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Victoria Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 08/01/2024
- Estimated End Date
- 05/06/2024
What we are doing
Between 8 January 2024 and 5 June 2024, we will be carrying out utility works to install a new cable diversion under Victoria Road. The planned works will include excavation and resurfacing of the road, and cabling works to create the diversion. These works will be carried out in phases.
Working Hours
Due to anticipated network requirements, our working hours will be as follows:
- From 8 January to 26 March 2024, 8am to 6pm, Monday to Friday and 8am to 1pm on weekends, and
- From 27 March to 5 June 2024, 8am to 10pm, Monday to Friday and 8am to 6pm on weekends.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]