Notice of Utility works on West End Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-07/07/22

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
West End Road
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Footpath closures, Haul road construction, Utility works / surveys
Estimated Start Date
25/07/2022
Estimated End Date
11/09/2022

What we are doing

What we are doing
Before we start tunnelling later this year, we plan to complete major utility works on West End Road, between 25 July and 11 September 2022.

These works are to strengthen and protect utilities from settlement (small movement in the ground caused by constructing the tunnels). The works will involve:
• Installing and diverting gas and water pipes
• Installing sewer lining. From 22–26 August this will be conducted overnight when sewer flows are lowest and can be managed with a tanker rather than over pumping. Lower flows also reduce       the number of tankers required
• Installing a temporary haul road
• Setting up a site compound within the Sidmouth Drive car park and installing fencing to segregate our work area

We will need to extend our normal working hours to reduce the overall time needed to complete these works.

There are likely to be additional works affecting utilities on West End Road, which we will let you know about as soon as possible.

How these works might affect you
From 25 July to 7 August 2022 Monday to Saturday 8am to 6pm Sunday 10am to 4pm:

Footpath closure while we Install of water valves Suspension of six parking bays on West End Road and footpath diversion in place

From 15 August to11 September 2022 Monday to Saturday 8am to 6pm and Sunday 10am to 4pm:

Temporary lane closure on West End Road to facilitate lining of existing gas and sewer
Footpath diversion and temporary pedestrian crossing located either side of the works area.
Suspension of fifteen parking bays on the northern side
Berkeley Close bus stop C and D and Ruislip Gardens stop B will be suspended and relocated as close as possible by Transport for London

Night work from 22 to 26 August Monday to Friday 7pm to 7am:

Tankering activities during the sewer lining works

Traffic along West End Road will be able to flow in both directions. However, due to the lane closure on northbound, only one lane of traffic will be able to flow at any one time. Please see map overleaf for the location of our works.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.