Notice of utility works preparation near Common Lane, south of King’s Bromley
Work item: HS2-MW-UT-Ph1-Ar-No-N1-UT-45-02/08/2022
Work Item Summary
- Project Phase
- Phase 2a
- Region
- Staffordshire
- Location
- Common Lane
- Worksite Name
- Common Lane, Kings Bromley
- Contractor
- Cadent Gas
- Type of works
- Utility works / surveys
- Estimated Start Date
- 04/03/2022
- Estimated End Date
- 29/04/2022
What we are doing
Before we start main work to move the pipeline, we will be carrying out some preparaion activities, in early March 2022. The work will involve:
• setting up a site access off Common Lane. Vehicles will use the existing bridlepath to access our working area.
• carrying out archaeological works and preparation activities on land off Common Lane, including digging trenches.
Vehicles will be accessing our working area from Common Lane, via the A515 northbound. We will be using our existing temporary works compound on land off Common Lane, south of King’s Bromley, to carry out this work.
There will be 24-hour security on site so we can maintain a safe working environment. Please note, there will be no on-site lodging.
How will this affect you?
So that our vehicles can enter and exit the site safely, Common Lane will only be accessible to residents and our construction vehicles. Signage will be installed on the roadside at this location to make road users aware.
All work will take place within standard HS2 working hours, and will be undertaken using standard industry methods. As the work progresses we will send you notifications to let you know what will be happening.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]