Notice of utility works preparation near Hanyards Lane, east of Stafford

Work item: HS2-EW-UT-Ph2A-UT-14-09/12/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Brancote
Worksite Name
Hanyards Lane
Contractor
Cadent Gas
Type of works
Utility works / surveys
Estimated Start Date
03/10/2022
Estimated End Date
16/12/2022

What we are doing

Cadent is moving an underground gas pipeline near Brancote, east of Stafford. Main works to move the pipeline is planned to start in March 2023 and Cadent expects all work will be completed by October 2023.

Before the main work to move the pipeline starts, Cadent will carry out some preparation activities from early-October until mid-December 2022.