Notice of vegetation clearance in Coleshill and Water Orton
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Eco-1-07/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Coleshill, Water Orton
- Contractor
- BBV JV
- Type of works
- Vegetation clearance
- Estimated Start Date
- 15/03/2022
- Estimated End Date
- 31/05/2022
What we are doing
BBV will be completing vegetation clearance works in locations across Coleshill and Water Orton from March 2022 until May 2022. The works will be completed in order to create space for working areas or to create accesses. All necessary permits will be in place prior to works being complete and where necessary, ecological surveys will be conducted prior to and during the works.
There may be times throughout the works where traffic management will be in put in place in order for us to carry out these works safely. In these instances, we will issue a notification and provide advance
warning. We will also notify about vegetation works that may affect particular stakeholders through a specific notification.