Notice of water connection works at Mandeville Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-26-02/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Northolt
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 05/03/2021
- Estimated End Date
- 15/03/2021
What we are doing
From Friday 19 February 2021, we will be carrying out water connection works in the area shown on the map in the below PDF notice. This will help us to install the water supply that will be used throughout our works site. Affinity Water will install the water supply at the entrance of Mandeville Road Vent Shaft site. These works will include the excavation of a trench to install connection pipes.