Notice of weekend road closures, A361, Chipping Warden
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-11-09/04/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Chipping Warden
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 10/05/2024
- Estimated End Date
- 20/05/2024
What we are doing
We are continuing to prepare the A361 in Chipping Warden for the permanent realignment of the highway over the Chipping Warden Green Tunnel. In May we will be moving the utilities which run near and under the existing road, near the HS2 Chipping Warden Compound.
A section of the A361 will require two weekend closures
• 8pm on Friday 10 May to 6am on Monday 13 May 2024
• 8pm on Friday 17 May to 6am on Monday 20 May 2024
Download information relating to these works