Notice of weekend road closures, A361, Chipping Warden
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-11-09/04/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Chipping Warden
- Contractor
- EKFB JV
- Type of works
- Road closure, Utility works / surveys
- Estimated Start Date
- 17/05/2024
- Estimated End Date
- 03/06/2024
What we are doing
We are continuing to prepare the A361 in Chipping Warden for the permanent realignment of the highway over the Chipping Warden Green Tunnel.
In May we will be moving the utilities which run near and under the existing road, just north of the village. We will also be carrying out additional work in the verges of the A361. This is in preparation for the installation of safety barriers, which will allow our workforce to start building the new section of highway.
A section of the A361 will require two weekend closures to complete this work safely.
When will these works take place?
A361 weekend road closures:
• 8pm on Friday 31 May to 6am on Monday 3 June 2024
• 8pm on Friday 14 June to 6am on Monday 17 June 2024
With a contingency weekend of 8pm on Friday 21 June to 6am on Monday 24 June 2024
This work is subject to approvals from the local authority and the dates of the work may change.