UPDATE: Notice of weekend road closures, Greatworth Temporary Road, Greatworth
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-32-16/08/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Greatworth
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 31/01/2025
- Estimated End Date
- 10/02/2025
What we are doing
To support the construction of the Greatworth Green Tunnel we will be building a plant crossing area for our heavy construction vehicles to cross the Greatworth Temporary Road. This plant crossing will be controlled by traffic lights and be in place for the duration of the tunnel construction. To build the crossing point we will be reinforcing the highway surface. This will require weekend road closures for up to three weekends, beginning on Friday 17 January 2025.
Weekend closures:
Completed weekend closures:
• 8pm Friday 17 January to 6am Monday 20 January 2025
• 8pm Friday 24 January to 6am Monday 27 January 2025
Cancelled weekend closure
• Friday 31January to Monday 3 February 2025
New weekend closure
• 8pm Friday 7 February to 6am Monday 10 February 2025