Notice of works outside core hours on the rail embankment and Flat Iron site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-06/09/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Flat Iron site
- Worksite Name
- Flat Iron site
- Contractor
- SCS JV
- Estimated Start Date
- 09/09/2023
- Estimated End Date
- 11/11/2023
What we are doing
From the Saturday 9 September to Wednesday 11 November, we will be carrying out further utility works on the alignment of the tunnels. These works will be taking place from 8am to 6pm on each day including weekend. The works being carried out will include excavation and installation of ducts and associated cables.