Notice of weekend works at West Ruislip
Work item: HS2-EW-SCS-PH1-Ar-So-S2-Prog-Works-28-26/052021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Ruislip
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 19/06/2021
- Estimated End Date
- 20/06/2021
What we are doing
What we are doing
We will be carrying out works over one weekend in the bell mouth where vehicles access the site from Ickenham High Road. We are connecting a foul sewer from site to a chamber that sits underneath the centre of the junction.
Once connected the trench will be backfilled and the work area reinstated. We will carry out the main cut into the concrete within normal working hours on the Friday 18 June, to minimise noise on the weekend.