Notice of Western Power Distribution Construction Works
Work item: HS2-EW-UT-Ph1-Ar-No-N2-UT-37-14/3/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- A452
- Worksite Name
- A452 Chester Road
- Contractor
- Western Power Distribution
- Type of works
- Excavation works, Road closure, Traffic management
- Estimated Start Date
- 14/03/2022
- Estimated End Date
- 31/03/2022
What we are doing
In order to prepare for the future Interchange Station and railway, Western Power Distribution need to carry out work on the A452 Chester Road outside Melbicks Garden Centre. The work will include excavating in the Southbound carriageway verge.
In order to undertake the work safely a southbound lane closure on A452 Chester Road will be in place from 7pm until 6am between Monday 14 March and Thursday 31 March 2022.
Additionally, temporary overnight closures of the southbound carriageway will be in place for two nights from 8pm until 6am on Tuesday 29 and Wednesday 30 March 2022.
Western Power Distribution has a responsibility for delivering electricity services to homes and businesses across the region, and will ensure that the impact of any work is kept to a minimum.
Where required, diversionary routes will be fully signed for road users.