Notice of work at Finmere Bridge, A4421
Work item: HS2-EW-EK-Ph1-Ar-Ce-C2-Prog-works-14-26/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Finmere
- Contractor
- EKFB JV
- Type of works
- Early construction works, Traffic management
- Estimated Start Date
- 01/02/2021
- Estimated End Date
- 31/07/2021
What we are doing
We are working at Finmere Bridge on the A4421 to create our haul and access road crossing. The work will involve a series of road closures at Finmere Bridge, Newton Purcell, to carry out the following activities:
- Vegetation clearance on the existing Finmere Bridge
- Surveys and trial holes
- Construction of a hard surface to support a crane
- Demolition of the existing Finmere Bridge
- Removal of the materials and remedial works
- Creation of the new access and haul road crossing
Work will be taking place from February in preparation for the demolition of Finmere Bridge. There will be traffic management and lane closures required on the A4421 from February to March to prepare the site. Traffic management will also be needed to complete any remedial works and tidy the site after the demolition has been completed.
There will also be a series of road closures on the A4421 at Finmere Bridge to carry out specific works.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]