Type of works
Drainage installation, Piling
Estimated Start Date
03/12/2023
Estimated End Date
25/02/2023

What we are doing

What we are doing
Mandeville Road site will be closed for the festive period from 24 December 2022 to 2 January 2023. Only maintenance and checks will be undertaken during this time as well as the usual security presence. Residents should not be disturbed with this work.

From 3 to 16 January 2023, we will be finalising the lower platform works area. A section of the current piling platform requires replacing and a drainage system needs to be installed to be ready for bored piling works which will start in mid-January.

From 16 January to 25 February 2023, we will be installing bored piles on the lower work area to create the foundations for the headhouse. We will install acoustic barriers to reduce the noise impact of these works.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.