Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-49-29/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Duddeston, Saltley
- Contractor
- BBV JV
- Type of works
- Grouting
- Estimated Start Date
- 07/11/2022
- Estimated End Date
- 11/11/2022
What we are doing
Ahead of constructing the new HS2 structures on Duddeston Mill Road we will need to carry out some work on a gas pipe which currently passes through our construction work area. To carry out this work we will need to excavate a small section of road on the junction of Duddeston Mill Road and Network Park Industrial Estate, we will then pour concrete into the hole to grout the gas pipe.
To be able to do this work safely we will need to put in place three-way temporary traffic lights from Monday 7 November until Friday 11 November on the junction of Duddeston Mill Road and Network Park Industrial Estate. The temporary lights will be manually operated during peak travel times to help to reduce congestion. Access to properties and businesses will be maintained throughout.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]