Notice of works – Footpath and Lane Closure Lawley Middleway

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-43-06/12/2023

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Aston
Worksite Name
Lawley Middleway
Contractor
BBV JV
Type of works
Footpath closures, Lane closure, Traffic management
Estimated Start Date
24/01/2024
Estimated End Date
01/02/2024

What we are doing

We will be removing some street lighting along a section of Lawley Middleway ahead of the installation of one of the new Curzon Viaducts that will carry HS2 trains over in the future.

In order to keep both the public and workers safe, we will require a short overnight footpath and lane closure from Wednesday 24 January 2024 for one week, between the hours of 10pm and 5am.

The footpath and lane closure will start on the South side, once complete we will then move to the North side.
Access will be maintained during these works