Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Rabournmead Drive
- Contractor
- SCS JV
- Type of works
- Vegetation clearance
- Estimated Start Date
- 08/11/2021
- Estimated End Date
- 12/11/2021
What we are doing
What we are doing
We wrote you in May to advise you that we would be carrying out sewer investigations near Rabournmead Drive. We need to re-visit this location to carry out additional works that will take place from 8 to 12 November 2021.
We will be clearing vegetation to undertake surveys of the sewer and manholes in the area, as shown on the map below.