Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Wendover
- Contractor
- Fusion JV
- Type of works
- Archaeology, Utility works / surveys, Worksite / compound set-up
- Estimated Start Date
- 05/10/2020
- Estimated End Date
- 31/03/2021
What we are doing
As part of our continuing works ahead of the construction of the railway we need to undertake some further work in your area. These works will consist of:
- Boundary Fencing
- Utility Surveys
- Preparation Works
- Archaeology
When will these works take place?
These works are planned to start in October 2020 and will be completed by March 2021. The site for the archaeology works is located between Bacombe Lane and Ellesborough Road. Access to the site will be from Bacombe Lane.