Notice of works in your area
Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-Works-18-09/05/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Euston station
- Worksite Name
- Euston Station
- Contractor
- Mace Dragados JV
- Type of works
- Gas Main Works
- Estimated Start Date
- 02/06/2025
- Estimated End Date
- 08/12/2025
What we are doing
We wrote to you in April 2025 to notify you of works taking place in the area (reference number: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-40-01/04/2025), including our gas works on Euston Street. Work is progressing on Euston Street, and we are continuing to enable the gas diversion. We expect these works to continue until September 2025. Please read the rest of this notice to find out more about the upcoming gas works taking place on Drummond Street and behind our hoarding.
Further information in the link below.
Keeping you engaged – in person engagement event
We will be holding a drop-in session on Saturday 24th May 2025, between 11am and 2pm at the Euston Community Hub on North Gower Street. At this event you will be able to find out about ongoing and upcoming works taking place in the area.
Please confirm your attendance by emailing: [email protected].
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]