Notice of works on Cobourg Street

Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-Works-14-23/02/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Cobourg Street, Euston station
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Hoarding works
Estimated Start Date
11/12/2023
Estimated End Date
08/03/2023

What we are doing

Update: New hoarding alignment on Cobourg Street (south)

We wrote to you in December 2022 to let you know that we are carrying out hoarding move works on Cobourg Street. We have now completed hoarding works at Cobourg Street (north) and are continuing to carry out works at Cobourg Street (south).

We are now extending the existing hoarding across the roadway to the edge of the western pavement to cover the worksite at Cobourg Street (south) until early March 2023. This is required to enable multi-utilities works which will be ongoing until November 2023 (subject to change). Additional lighting and CCTV will be added to the hoarding. As we install the hoarding, there will be no pedestrian access from Euston Street onto Cobourg Street between the hours of 8am to 5pm Monday to Friday.

During these times, pedestrians will need to walk via North Gower Street and Drummond Street to access the station. We apologise for any inconvenience caused whilst the hoarding is being installed.