Notice of works on Euston Road and Churchway
Work item: HS2-MW-MD-Ph1-Eu-St-S3-UT-1-17/02/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Churchway, Euston Road
- Contractor
- Mace Dragados JV, Vodafone
- Type of works
- Utility works / surveys
- Estimated Start Date
- 06/03/2023
- Estimated End Date
- 17/04/2023
What we are doing
Vodaphone utility diversion works will take place on the junction of Churchway and Euston Road. The eastbound bus lane adjacent to the working areas will be closed from Churchway to Midland Road during these works. The British Library bus stop C will be suspended during the Ossulston Street and Midland Road phased works. We will always maintain two lanes of eastbound traffic.
Chalton Street junction at Euston Road will be closed throughout these works except on market days when we will remove the closure to allow access for the market traders. Entry and way out of Chalton Street will be via Phoenix Road on all other days.
Ossulston Street junction at Euston Road will be closed throughout these works. This junction will remain open for cyclists only. Entry and way out of Ossulston Street will be via Phoenix Road on all other days.
The north side footpath on Churchway will be partially closed during this phase of works. There will be a pedestrian diversion around the work area.