Notice of works on Gordon Street

Work item: HS2-MW-MD-Ph1-Eu-St-S3-Traf-48-03/11/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden, Gordon Street
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Utility works / surveys
Estimated Start Date
20/11/2023
Estimated End Date
22/12/2023

What we are doing

From 20 November until late December 2023, UKPN will replace old infrastructure by retrieving and pulling cables on Gordon Street. During the work, Gordon Street (south bound, adjacent to Euston Road) will not be accessible to vehicles. Pedestrian access and crossings will remain in use throughout these works.

The construction will consist of breaking out sections of the existing highway, and reinstating the highway. We will not be working during the festive period and the road will reopen once the work is complete.