Skip to main page content
View route map

Notice of works on HS2 properties in Swinfen

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Prog-works-16-20/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire
Location
Swinfen
Worksite Name
Packington Moor Farm
Contractor
BBV JV
Type of works
Demolition works
Estimated Start Date
01/06/2022
Estimated End Date
30/09/2022

What we are doing

We will be commencing works to assess and safely dismantle properties and buildings on Packington Moor Farm and Knox’s Grave Lane. Before we start the dismantling work we will undertake asbestos and utility surveys to ensure the safety of our workforce. We will also complete ecological investigations prior to any work starting to ensure that we do not disturb any nesting birds and habitat at these locations.

These works are expected to start in June and will continue throughout Summer 2022. We will create a safe working area and our working hours will be between 8am and 6pm, Monday to Friday. Our workforce can be on site one hour before and after to set up and secure our equipment.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]