Notice of works on M42 Junction 7 Link Road

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-UT-5-16/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Coleshill
Contractor
BBV JV
Type of works
Lane closure
Estimated Start Date
03/10/2022
Estimated End Date
22/12/2022

What we are doing

The work we will be doing.

The new railway will cross the M6 on an over bridge near Junction 4. In order to safely build the southern abutment to this bridge we will need to close the hard shoulder on the slip road that connects the Northbound carriageway of the M42 to the Northbound carriageway of the M6.

When will these works take place.

The work will take place from Monday 3 October until Thursday 22 December. The hard shoulder will be closed 24/7 and our working hours will be 08:00-18:00 Monday-Friday. Should the works be completed sooner, we will re-open the hard shoulder as soon as it is safe to do so.