Notice of works on North Gower Street

Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-33-05/01/2023

Work Item Summary

Project Phase
Phase 1
Location
North Gower Street
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Monitoring equipment, Ramp removal
Estimated Start Date
05/08/2023
Estimated End Date
05/08/2023

What we are doing

Removal of Mobile Elevating Work Platform on North Gower Street on Saturday 5 August 2023

Works continue to progress at the former Maria Fidelis school site to deliver staff office facilities and the Construction Skills Centre. As part of this work, we need now to remove a mobile elevating work platform on Saturday 5th August for approximately 2 – 3 hours. The platform will be removed from site via a construction access gate located on North Gower Street – see plan below.

Pedestrian access will be maintained via a temporary walkway. Traffic marshals will also be in place to hold back pedestrians whilst the platform is removed from the gate for collection. Please be reassured that access/egress from George Mews properties will be maintained.