Notice of works on Robert Street and Hampstead Road

Work item: HS2-MW-MD-Ph1-Ar-No-N2-Traf-35-01/03/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Hampstead Road, Robert Street
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Survey
Estimated Start Date
13/03/2023
Estimated End Date
17/03/2023

What we are doing

Sewer surveys on Robert Street and Hampstead Road between 13 and 17 March 2023

As part of our essential programme of utilities works, we need to carry out CCTV surveys on the existing sewer to check its condition and collect information to assist with design works. The sewer manhole is located on Robert Street within the existing temporary work site and also at the junction of Hampstead Road/ North Gower Street.

Access to the manhole to carry out these surveys is required for approximately four nights in mid-March 2023. These surveys can only be carried out at night given that water flows are lower which means we can collect more accurate survey results. For location and traffic management details, please refer to the plan attached, below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]