Notice of works, sheet piling, Small Dean Lane

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-27-27/09/2021 1MC12-EKF-IN-NTE-CS04-000025

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Small Dean
Contractor
EKFB JV
Type of works
Construction
Estimated Start Date
22/10/2021
Estimated End Date
14/11/2021

What we are doing

What are we doing?
As part of our continued preparatory works for the construction of the Small Dean Viaduct, we need to install sheet piles adjacent to the existing rail line near Small Dean Lane. These works are vital to protect and secure the network rail line during the construction of the viaduct over the A413.
We are planning to carry out these works over four weekends.
During the works, a section of Small Dean Lane will be closed, with local diversion in place.
When will these works take place?
These works can only be done under Network Rail possession of the rail line. We will work Friday night to Sunday night, for 24 hours, over four weekends to get the work completed as quickly as possible. A section of Small Dean Lane will be closed during the weekends these works take place. The weekends these works are scheduled to take place are the following: 22nd -24th October, 29th-31st October, 5th-7th November and 12th-14th November.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]