Notice of works to Kelsey Lane and Waste Lane – Balsall Common
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-42-05/09/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Balsall Common
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 25/09/2023
- Estimated End Date
- 06/10/2023
What we are doing
As you may be aware, following consultation with residents, BBV and HS2 have been working closely with Solihull Metropolitan Borough Council (SMBC) on a series of traffic calming measures on Kelsey Lane and Waste Lane. This includes three radar speed signs, three chicanes and the introduction of a 20mph speed limit.
In order to do this work safely we will need to introduce traffic management on Kelsey Lane, Waste Lane and the top of Windmill Lane in two phases over a two-week period beginning on 25 September. To minimise disruption, we will limit our working hours to 9:30am until 3:30pm and we will also reduce the extent of the closures as our work completes.
Phase One – 25-29 September
Part of Waste Lane from Little Beanit Farm to Hodgett’s Lane will be closed. Access for residents will be maintained and traffic will be diverted via Burton Green
Kelsey Lane and the remainder of Waste Lane will be reduced to one lane and controlled by temporary traffic lights.
Phase Two – 2-6 October
Kelsey Lane and Waste Lane will be fully closed. Access for resident will be maintained and traffic will be diverted via Burton Green
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]