Notice of works to start excavating Westgate ventilation shaft

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-7-24/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Westgate
Worksite Name
Westgate
Contractor
SCS JV
Type of works
Excavation works
Estimated Start Date
09/08/2021
Estimated End Date
30/11/2021

What we are doing

Works to build a ventilation shaft from July 2021

From late July 2021, we will start works to build the ventilation shaft at our Westgate site. This will be 15 metres wide and about 43 metres deep to connect to the HS2 tunnels. We will start constructing the tunnels in this area from 2023.

Our construction team will build the ventilation shaft in stages:
1. We will install a concrete collar around the top of the shaft to support the ground.
2. We will install concrete rings and excavate the ground in layers to build the shaft.
3. When the ventilation shaft reaches about 11 metres below ground, we will continue excavation in layers and apply sprayed concrete lining (SCL) until the shaft reaches its depth of about 43 metres.

The map on the following page shows the location of these works.

Our working hours
During July and most of August, we will be working from 8am to 6pm on Mondays to Fridays and 8am to 1pm on Saturdays. From late August, we will extend our working hours to 24 hours a day on Mondays to Fridays. We will continue to work on Saturdays from 8am to 1pm. Both dates remain subject to change.