Notice of works to the South of Euston Station
Work item: HS2-MW-MD-Ph1-Eu-St-S3-UT-1-04/01/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Euston Road
- Worksite Name
- Euston Station
- Contractor
- Mace Dragados JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 09/01/2023
- Estimated End Date
- 28/02/2023
What we are doing
Utilities trial holes in Euston Road footpath
From 10 January to end February, we will undertake trial holes in several locations on Euston Road along with some ducting works for UK Power Networks. The trial holes will establish what services are below ground at each location and will not affect utility connections to buildings. We will be in each location for around two to four weeks, and works will be phased to manage disruption.
Trial holes will take place in the footpaths and bus lanes of Euston Road. There will be pedestrian diversion routes around the worksites and localised bus lane closures adjacent to the working areas (between North Gower Street and Eversholt Street). While working on the south side, bus stop P outside the Wellcome Trust will be suspended with the closest available stops being bus stop W and bus stop CH. Bus stop AZ will remain open but will be temporarily relocated to the west for two weeks. Please see map in the document below.
Junction alterations for taxi rank and bus station
In order to build the new Euston London Underground interchange, we need to move the current taxi rank from Euston Square Gardens (west) to Euston Square Gardens (east), where it will remain for the rest of the HS2 construction period.
Construction works for the new taxi rank continue until Spring 2023, and include installing a canopy, building a new cycle ramp and making adjustments to junctions at Euston Road/Euston Grove and Eversholt Street. Please see map in the document below.
Weekend closures of Euston bus station
We need to close Euston bus station for three consecutive weekends starting on 27-29 January, 3-5 February, and 10-12 February (from Friday 21:30 hrs to Sunday 23:59 hrs.) This is to widen the junction between the bus station and Eversholt Street to accommodate taxis in future. Please see map in the document below.