Notice of Works to Upgrade the Gas Main on Alperton Lane
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-06/04/23
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Alperton Lane
- Worksite Name
- Westgate
- Contractor
- SCS JV
- Type of works
- Gas Main Works
- Estimated Start Date
- 09/05/2023
- Estimated End Date
- 25/08/2023
What we are doing
From 9 May 2023 to 25 August 2023, we will be upgrading the gas main on Alperton Lane. This will occur in four phases.
The works will take place between 8am to 6pm Monday to Friday and 8am to 1pm Saturdays, if required.
Phase one: Lane closure, partial footpath closure and parking suspensions on Alperton Lane.
Phase two: Lane closure, partial footpath closure and parking suspensions on Alperton Lane.
Phase three: Lane closure, partial footpath closure and parking suspensions on Alperton Lane. Temporary road closure with a partial road closure on May Gardens.
Phase four: Lane closure, partial footpath closure and parking suspensions on Alperton Lane.
Some residents may require a possible replacement and relocation of their gas meter, these residents would have received a letter explaining the process.