Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Duddeston
- Contractor
- BBV JV
- Type of works
- viaduct works
- Estimated Start Date
- 02/05/2026
- Estimated End Date
- 05/05/2026
What we are doing
Location
Duddeston
Duration
These works will be between Saturday 2 May 2026 to Tuesday 5 May 2026 and will require a 24-hour working pattern.
What we are doing
As works are progressing in the area, we will now be launching the Duddeston Viaduct over the existing Network Rail lines. This is a key part of the route that will carry High Speed trains from the East of Birmingham and into Curzon Street Station, right in the centre of Birmingham.
What to expect
This work will have no highway impacts as it is over the existing Network Rail lines. It will require a 24-hour working pattern so there be some low-level construction noise and lighting overnight.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.