Notification of keep clear road markings
Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-65-23/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Worksite / compound set-up
- Estimated Start Date
- 22/10/2022
- Estimated End Date
- 22/10/2022
What we are doing
Keep Clear road markings
As part of our site entrance set-up activities, we will be painting ‘Keep Clear’ signs on the road directly outside of our vehicle site entrance. We have included a map on the next page showing the location of this activity.
This will allow the current three-way traffic lights to be removed eventually and to improve the safety of vehicles entering and leaving our site from Old Oak Common Lane.
This work will take place outside of our normal working hours as the traffic on Old Oak Common Lane will be limited. We currently expect this to take place on Saturday 22 October 2022 between 2pm and 6pm. The work is weather dependant so if it does not take place on this date, we will update you.
For safety reasons we will be closing one lane at a time whilst this work is being carried out. To ensure the flow of traffic is not disrupted more than necessary, we will have three traffic control operators who will guide traffic with ‘Stop/Go’ signs.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]