Notification of traffic management Leicester Lane, Cubbington

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-34-10/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Cubbington
Worksite Name
Leicester Lane
Contractor
BBV JV
Type of works
Road closure, Traffic management
Estimated Start Date
06/06/2022
Estimated End Date
08/07/2022

What we are doing

Notification of traffic management Leicester Lane, Cubbington.

In order to construct and complete our site access safely, we need to close Leicester Lane. Following this, we will be undertaking works on the verges of the road, with temporary traffic lights used overnight and when the closure is lifted.
Two fully signed diversions will be in place during the closures, one for HGV’s and one for local traffic. Access to all properties will be maintained throughout these closures.

These works will take place as shown below.

From Monday 6 June 2022 to Friday 17 June, we will be closing Leicester Lane between 8am and 6pm Monday to Friday with temporary traffic lights in place outside of these hours. There will be no traffic management during the weekend of the 11 and 12 June 2022.

Due to our works proceeding more efficiently than expected we have reduced the requirement for traffic management as shown below.

  • From Monday 20 June to Friday 24 June, temporary traffic lights will be in place 24 hours a day seven days a week.
  • From Wednesday 29 June to Friday 1 July a full closure of Leicester Lane will be in place between the hours of 9am and 6pm.
  • On Monday 4 July temporary traffic lights will be in place from 9.30am to 3.30pm
  • From Wednesday 6 July until Friday 8 July temporary traffic lights will be in place, 24 hours a day.

Our working hours will be 8am to 6pm. Our workforce maybe onsite one hour before and one hour after to set up and secure our equipment.

No weekend work will take place.